Team Orange successfully complete culvert installation work near Exeter as part of £26.5m flood alleviation scheme for the south west

coley culvert 1 cowley 1 cowley 2

 Cowley area Culvert.(Network Rail Images)

The Great Western Mainline near Exeter in Devon reopened as planned this morning following the successful completion of culvert installation work by Network Rail’s Team Orange.

Engineers have been on site since Tuesday, working to install a new relief culvert at Cowley Bridge as part of a wider flood alleviation scheme to help improve resilience of the railway.

Flooding in the Cowley area has been a longstanding problem which has had a devastating impact on this part of the Great Western Mainline, resulting in numerous delays and closures.

Thirty-five members of Team Orange have been working around the clock since Tuesday 12 June to install twenty-four culvert units – hollow concrete rectangular structures – which will reduce the likelihood and severity of flooding on the railway. Each unit weighs approximately 14 tonnes and measures 4.1 metres wide by 2.1 metres tall.

Work will continue at Cowley Bridge until the end of the year, as Team Orange enlarge an existing culvert in the area to further improve the railway’s resilience.

Victoria Bradley, Network Rail’s sponsor for the project said:

“I’d like to thank passengers for their patience as we completed the installation of this brand new culvert, which is an important step forward in our Exeter flood resilience work.

“This project, along with our other flood resilience schemes in the region, will significantly reduce the number of times the south west is cut off during periods of extreme weather, reducing delays and improving passengers’ travelling experiences.”

The Cowley culverts project is one of a number of schemes under the Department for Transport’s Flood Resilience Programme. This £26.5m programme was established after extreme weather in 2012 and 2014 caused extensive disruption to the rail network. The aim of the programme is to reduce the risk of flooding at key locations in the Thames Valley and south west and ensure that when flooding does occur, train services can be resumed at a quicker rate, reducing disruption for passengers.

Managing director of CrossCountry, Andy Cooper, said:

“Completing this work in such a short period of time means Network Rail have kept any disruption for our customers to a minimum. Extreme weather is increasingly causing problems for train services and this work at Exeter will ensure the railway is more resilient, helping maintain Devon and Cornwall’s important rail connections to the rest of Britain”.